Day 3: Pour Slab

Paint the exterior of the precast panels which is usually done in a rendered paint e.g. Wattyl Granolmpact or Taubman Armawall depending on the finish the client has selected. Texture rollers can do around windows and doors without cutting in before windows are...

Day 2: Plumbing & Preparation

The props can be removed once above is completed. The plumber can do all the internal drainage works and the local government can come to inspect the drainage. The precast panels can be primed ready for painting. The electrician can install the main power meter box...