by Mick Johnson | Mar 4, 2020
The home should be all locked up and ready for you to send the lock up invoice to your client.
by Mick Johnson | Mar 4, 2020
The Plumbing, electrical & ducting can be started if appropriate. The roof can be finished and eaves placed. Install all external doors.
by Mick Johnson | Mar 4, 2020
Start roof, fascia and gutter. Place frames (pre-fab or onsite construction). These can be walked through garage/alfresco/panel openings. Install Windows.
by Mick Johnson | Mar 4, 2020
Paint the exterior of the precast panels which is usually done in a rendered paint e.g. Wattyl Granolmpact or Taubman Armawall depending on the finish the client has selected. Texture rollers can do around windows and doors without cutting in before windows are...
by Mick Johnson | Mar 4, 2020
The props can be removed once above is completed. The plumber can do all the internal drainage works and the local government can come to inspect the drainage. The precast panels can be primed ready for painting. The electrician can install the main power meter box...